City Plans And Projects

Project Name  Current Status % Complete
Northside Study/
Housing Study
Second Community Plan held on 8/27/18.  100%
Old Mill Site
Clean Up
Phase I ESA
Phase II ESA
Project award to Complete Demolition Services. Scheduled for Council approval Aug 11/15.  
80%
Maintenance & Sanitation Admin Building Currently on hold. N/A
City Hall Renovations Door Hardware is complete. Restroom renovations are on hold until after Wednesday Wind Down is over. DeNyse is finished with installing all new signage. 

Interior 90%
Exterior Roofing & Painting 100%
Old Jail/Downtown
Master Plan
RFB deadline was July 17th. 7 bids were received. City staff are reviewing all bids for accuracy and calling references.  Asbestos contractor is underway with providing an asbestos report for the site. Asbestos will be removed before demolition begins. 

Agreement for demolition is scheduled for approval by Mayor and Council Aug 11/15. 

Agreement for Phase 1 & 2 of downtown Masterplan has been approved by Mayor and Council.  

75% complete
Fleet Study  Faster software will go live by June 2019.
100%
City Branding Study Complete. Branding guide submitted to City. 100%
Mill Village/Willing Workers Park Renovations Bid Awarded to GMC.  GMC will present a detailed schedule for Mill Village and Willing Workers. Legal is working with property owner to acquire land at Willing Workers.  25%
Hawthorne Center Restroom Renovations Project is complete. 100%
Unified Development Code Rewrite Deadline for draft from Jacobs is February 1. 100%
Douglasville Comprehensive Plan Update Public hearing held on 8/30/18. 90%, must be complete by October 31
 Windshield Study Old Mill Village and Downtown area  100%
 Riverside Parkway Bridge Rehab Project ready to go to construction in 3 months.
Sent letter to GDOT to move up the construction.
 35%
 Dallas Highway LCI Study Download the Plan. (File is 27 mb)
See the Steering Committee presentation from 5/3/19 meeting. See earlier presentations from 1/18/19 and 3/28/19. Presentation to Council on 8/1/19. City Council Meeting scheduled for August 1 & 5, 2019. 
40%
 Colquitt Terrace Construction is in progress.  Construction - 100%
 PD Community Center Parking Lot Project is complete.  100%
 SPLOST Resurfacing Bid Package Bartow Paving will begin resurfacing at the first of September 2019, after Labor Day.   Design - 100%
 SPLOST Proposed Project List and Schedules

List of remaining projects in the SPLOST program turned in for review. 90% 
 Douglas Boulevard Resurfacing C.W. Matthews will begin resurfacing at the  first of September 2019, after Labor Day. 

 Preliminary Design - 5%
 I-20 @ SR 92 Interchange Enhancements GDOT encroachment permit has been submitted.
Due to planting season requirements, project will bid in late summer. Plans are complete and the RFP is being finalized to begin bidding in early August. 
Design – 95% complete. Awaiting approved encroachment permit. 
 Lighting & Banners Phase II Curb and Gutter Construction completed. Project under budget. No change orders.  100% completed
SR92/Dallas Hwy Enhancements   Conceptual design is in progress by APD. Concept design - 80% 
 SR92/Fairburn Road Enhancements
 Conceptual design is in progress. Also includes Veteran’s Memorial from Campbellton Street to the Old Mill.
Concept Design – 50% for Fairburn Road, 10% for Veteran’s Memorial. AECOM is scheduled to present the Veterans Memorial concept to council on August 5th. 
 Cedar Mountain Road Roof is complete and they have started installing interior walls.
 15%
 West Court House Square  Demo of the interior began on July 8th. Still in demo phase.   Contract with Ra-Lin has been signed.
 Club Drive Project  TBA  
 Pedestrian Bicycle Plan  AECOM is gathering data and mapping. AECOM and the city met with ARC on June 13, 2019.   10%
 I-20 @ Chapel Hill Interchange Douglas County is the project manager. First Steering Committee meeting. The city is on the steering committee. There are some questions about Freedom Island.    
 Comprehensive Transportation Plan Update (CTP)   Signed contract with Jacobs. Started study on June 12, 2019. Kick-off meeting with Jacobs on July 9, 2019.   

 SPLOST 172x114
SPLOST Projects
 DOUGLASVILLE_MPLAN_172x114
Downtown Master Plan &
10 Year Strategic Plan


Chandler Thinks logo 172x114
Douglasville Branding Study
AE Comm logo p1191
Douglasville SPLOST Update
SR 92 at CVS for p1191
State Route 92 Project
 
Comp Plan 071918 gfx172x114 
City/County Comprehensive Plan

Goals and Objectives on 1191
Goals and Ojectives