City Plans And Projects

Project Name  Current Status % Complete
Northside Study/
Housing Study
Second Community Plan held on 8/27/18.  100%
Old Mill Site
Clean Up
Phase I ESA
Phase II ESA
Monitoring wells have been installed.  Survey is underway. RFB is due July 12th.


80%
Facilities Assessment Study  30 of 30 facility assessments are complete. Staffing assessment contract under review.
100%
Maintenance & Sanitation Admin Building Currently on hold. N/A
City Hall Renovations Door Hardware is complete. Restroom renovations are on hold until after Wednesday Wind Down is over. Some signs are installed.  DeNyse should be back next week to install the rest.

Interior 90%
Exterior Roofing & Painting 100%
Old Jail/Downtown
Master Plan
Site has been cleared for demolition.  RFP has been issued and is due July 10th. 
Agreement for Phase 1 & 2 of downtown Masterplan has been approved by Mayor and Council.
75% complete
Parks Master Plan Complete  100%
Maintenance Facility at Hunter Park Project has been cancelled. N/A
Pay and Compensation (Evergreen) Study Complete. 100%
Fleet Study  Faster software will go live by June 2019.
100%
City Branding Study Complete. Branding guide submitted to City. 100%
Mill Village/Willing Workers Park Renovations Bid Awarded to GMC. GMC presented draft concept to Mayor and Council. Awaiting approval of Consulting Services Agreement.  20%
Hawthorne Center Restroom Renovations Project is complete. 100%
Unified Development Code Rewrite Deadline for draft from Jacobs is February 1. 100%
Douglasville Comprehensive Plan Update Public hearing held on 8/30/18. 90%, must be complete by October 31
 Windshield Study Old Mill Village and Downtown area  100%
 Riverside Parkway Bridge Rehab Project ready to go to construction in 3 months.  35%
 Dallas Highway LCI Study Final draft being prepared. 
See the Steering Committee presentation from 5/3/19 meeting. See earlier presentations from 1/18/19 and 3/28/19.
40%
 Colquitt Terrace Construction is in progress.  Constructiion - 95%
 PD Community Center Parking Lot Project is complete.  100%
 SPLOST Resurfacing Bid Package Contract with Bartow Paving is being executed.   Design - 100%
 SPLOST Proposed Project List and Schedules

List of remaining projects in the SPLOST program turned in for review. 90% 
 Douglas Boulevard Resurfacing Contract with CW Matthews is being executed.
 Preliminary Design - 5%
 I-20 @ SR 92 Interchange Enhancements GDOT encroachment permit has been submitted.
Due to planting season requirements, project will bid in late summer
Design – 95% complete. Awaiting approved encroachment permit. 
 Lighting & Banners Phase II Curb and Gutter Construction completed. Project under budget. No change orders.  100% completed
SR92/Dallas Hwy Enhancements   Conceptual design is in progress by APD. Concept design - 80% 
 SR92/Fairburn Road Enhancements
 Conceptual design is in progress. Also includes Veteran’s Memorial from Campbellton Street to the Old Mill.
Concept Design – 50% for Fairburn Road, 10% for Veteran’s Memorial.
 Cedar Mountain Road 1/3 complete. Construction of the building has begun. 
 15%
 West Court House Square  First Environmental is scheduled to begin the abatement process on 6/17/19.  Should take 7 – 14 days to complete.  Contract with Ra-Lin has been signed.
 Club Drive Project  TBA  
 Pedestrian Bicycle Plan  GIS is in progress; AECOM has coordinated with Douglas County and ARC.  10%

 SPLOST 172x114
SPLOST Projects
 DOUGLASVILLE_MPLAN_172x114
Downtown Master Plan &
10 Year Strategic Plan


Chandler Thinks logo 172x114
Douglasville Branding Study
AE Comm logo p1191
Douglasville SPLOST Update
SR 92 at CVS for p1191
State Route 92 Project
 
Comp Plan 071918 gfx172x114 
City/County Comprehensive Plan

Goals and Objectives on 1191
Goals and Ojectives