SPLOST Paving Update

Post Date:09/05/2019

CW Matthews will have the Douglas Boulevard resurfacing project essentially complete by Saturday 9/28/19. Permanent thermo-stripe will be the only remaining work for the project to be complete.

The second major project is the 2019 SPLOST bid package being done by Bartow Paving during daylight hours.

Here is the updated schedule from Bartow Paving:

Week of September 30 thru October 4, 2019

Asphalt Milling/Resurfacing

  1. Oakvale Drive 
  2. Malone Street 
  3. Presley Place 
  4. Charlton Way 
  5. Raleigh Way

Note: This schedule is subject to change due to weather conditions or any unforeseen circumstances beyond our control.

For questions, comments or complaints please contact the Public Services Department at (770) 920-3005 or e-mail us at sanitation@douglasvillega.gov.

SPLOST Paving Update

Return to full list >>

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Download Acrobat Reader Flash Player Download Flash Player Windows Media Player Download Windows Media Player Microsoft Silverlight Download Microsoft Silverlight Word Viewer Download Word Viewer Excel Viewer Download Excel Viewer PowerPoint Viewer Download PowerPoint Viewer