City Plans And Projects

Print
Press Enter to show all options, press Tab go to next option
Project Name Current Status % Complete
Northside Study/
Housing Study
Second Community Planheld on 8/27/18. 100%
Old Mill Site
Clean Up
Phase I ESA
Phase II ESA
Clean up is about 75% finished.
80%
Maintenance & Sanitation Admin Building Currently on hold. N/A
City Hall Renovations Upstairs restrooms should be complete before Christmas. 
Interior 90%
Exterior Roofing & Painting 100%
Old Jail/Downtown
Master Plan
Demo party was held on Nov 18th. 
Asbestos Abatement has commenced, demolition will follow.
 
 
Fleet Study Faster software will go live by June 2019. 100%
City Branding Study Complete. Branding guide submitted to City. 100%
Mill Village/Willing Workers Park Renovations Agreement with Integrated Construction and Nobility, Inc. for construction of Mill Village Park Improvements project approved at council meeting on 12/16/2019.  50%-Bid Opening for Mill Village RFP on 11/22 and Willing Workers status pending regarding purchase of property. City Legal is communicating with property owner. The property owner has begun the probate process needed to clear the land title, and it is on-going.
Hawthorne Center Restroom Renovations Project is complete. 100%
Unified Development Code Rewrite Deadline for draft from Jacobs is February 1. 100%
Douglasville Comprehensive Plan Update Public hearing held on 8/30/18. 90%, must be complete by October 31
Windshield Study Old Mill Village and Downtown area 100%
Riverside Parkway Bridge Rehab Project ready to go to construction in 3 months.
Sent letter to GDOT and ARC to move up the construction. GDOT stated they would if FFPR was done and Env, ROW and Utilities were certified. Working on that now.  Applied for the 3rd Quarter Tip Amendment for $33,000 in additional funds for construction. ARC shows the additional money in the TIP Amendment. FFPR was submitted and Env, ROW and Utilities were certified. 
35%
Dallas Highway LCI Study Download the Plan. (27MB)
See the Steering Committee presentation from 5/3/19 meeting. See earlier presentations from 1/18/19 and 3/28/19. Presentation to Council on 8/1/19. Final Draft prepared. Went to City Council work session on August 1, 2019. City Council approved the Final Draft and costs September 3, 2019. Staff is submitting the final draft to ARC. ARC stated that it was complete.  
100%
Colquitt Terrace Construction is in progress. Construction - 100% complete.
PD Community Center Parking Lot Project is complete. 100%
SPLOST Resurfacing Bid Package SPLOST list was presented to Marcia and Greg in June. The final list needs to be determined and will be bid in Spring 2020.  Design - 100%
SPLOST Proposed Project List and Schedules
List of remaining projects in the SPLOST program turned in for review. 90%
Douglas Boulevard Resurfacing Project is complete except for installing the traffic signal vehicle loop detectors.  
 
I-20 @ SR 92 Interchange Enhancements

Project has been awarded to Russell Landscape Contractors. Execution of contract is in progress. 

 
Lighting & Banners Phase II Curb and Gutter Construction completed. Project under budget. No change orders. 100% completed
SR92/Dallas Hwy Enhancements The concept development is complete, and estimates were provided for design and construction. Funding sources are now being sought to fund them.  Concept design - 80%
SR92/Fairburn Road Enhancements The AECOM cost proposal for the design was submitted on November 22nd.   Concept Design – 75% for Fairburn Road, 75% for Veteran’s Memorial.
Cedar Mountain Road CO anticipated in the next 2-3 weeks. Punch tentatively scheduled for Jan 8th. Furniture delivery January 6th. Ribbon cutting on 2/13/20. Flooring install in progress. Electronic security installation in progress. 85%
West Court House Square Substantial completion is anticipated mid-February. Ra-Lin CO#1 placed on 12/12 agenda for approval. Drywall installed. Windows to begin being installed next week. Building is 2-3 weeks from being dried in.       56%
Club Drive Project CPS to get pre-engineered building company to make site visit to provide budget number for replacing roof and exterior of maintenance building. Once received, CPS will draft design/build RFP to be issued after January 1st.  
Pedestrian Bicycle Plan AECOM is gathering data and mapping. AECOM met with the Steering Committee on Sept. 3, 2019. Steering Committee met Wednesday, November 20. They had a lot of data and recommendations.  10%
I-20 @ Chapel Hill Interchange Miguel Valentin presented a power point presentation to the CC. A Stakeholders meeting was on Wednesday, November 6, 2019.  Freedom Island- Went before City Council on August 15, 2019. City Council determined to make it a park. We are having it surveyed now. Received a quote from Vansant Campbell for surveying of $1700. Douglas County showed a preferred alternative to keeping Freedom Island to the City Council.  
Comprehensive Transportation Plan Update (CTP) Signed contract with Jacobs. Started study on June 12, 2019. Kick-off meeting with Jacobs on July 9, 2019.Jacobs is doing data collection. Jacobs went to a community event and surveyed citizens on 8-14-19. Steering Committee Meeting was on Tuesday, November 19th, 2019. 
Conference Center A/V Equipment/System Project put on hold until FY21. 

LMIG 2019 Resurfacing

 Opened bids and CW Matthews said they should be finished by the end of 2019.   Contracts are being generated.

 Ellis Street

Improvements to Ellis Street from the SR 92 Underpass to Huey Road- AECOM Task Order 21 has been approved.   
 Hunter Park Walking Trail  The scope is to construct a 10’ paved walking path in the same footprint of the former kids train next to Ike Owings Community Center.  Construction costs for asphalt versus concrete alternatives to be presented to Council on December 12th.   

Additional Resources

SPLOST ProjectsSPLOST Projects

Downtown Master Plan & 10 Year Strategic PlanDowntown Master Plan & 10 Year Strategic Plan

Douglasville Branding StudyDouglasville Branding Study

Douglasville SPLOST UpdateDouglasville SPLOST Update

State Route 92 ProjectState Route 92 Project

City-County Comprehensive PlanCity/County Comprehensive Plan

Goals and ObjectivesGoals and Objectives (coming soon!)

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Download Acrobat Reader Flash Player Download Flash Player Windows Media Player Download Windows Media Player Microsoft Silverlight Download Microsoft Silverlight Word Viewer Download Word Viewer Excel Viewer Download Excel Viewer PowerPoint Viewer Download PowerPoint Viewer