Project Name Current Status % Complete
Northside Study/
Housing Study
Second Community Planheld on 8/27/18. 100%
Old Mill Site
Clean Up
Phase I ESA
Phase II ESA
Pre-Con meeting was held Aug 29th.
EPD conducted a site visit on Aug 29th and will send final closeout report week of Sept 2nd.
Clean up will commence in the next 30 days.
80%
Maintenance & Sanitation Admin Building Currently on hold. N/A
City Hall Renovations Downstairs restroom renovations are underway.
Interior 90%
Exterior Roofing & Painting 100%
Old Jail/Downtown
Master Plan
Asbestos contract will be awarded to Complete Demolition Services.
Asbestos abatement and archaeologist check will be conducted at the same time.
75% complete
Fleet Study Faster software will go live by June 2019. 100%
City Branding Study Complete. Branding guide submitted to City. 100%
Mill Village/Willing Workers Park Renovations Bid Awarded to GMC. 35%- Schedule for Mill Village and Willing Workers provided by GMC. Legal is working with property owner to acquire land at Willing Workers. 
Hawthorne Center Restroom Renovations Project is complete. 100%
Unified Development Code Rewrite Deadline for draft from Jacobs is February 1. 100%
Douglasville Comprehensive Plan Update Public hearing held on 8/30/18. 90%, must be complete by October 31
Windshield Study Old Mill Village and Downtown area 100%
Riverside Parkway Bridge Rehab Project ready to go to construction in 3 months.
Sent letter to GDOT and ARC to move up the construction. GDOT stated they would if FFPR was done and Env, ROW and Utilities were certified. Working on that now.  Applied for the 3rd Quarter Tip Amendment for $33,000 in additional funds for construction. ARC shows the additional money in the TIP Amendment. 
35%
Dallas Highway LCI Study Download the Plan. (27MB)
See the Steering Committee presentation from 5/3/19 meeting. See earlier presentations from 1/18/19 and 3/28/19. Presentation to Council on 8/1/19. Final Draft prepared. Went to City Council work session on August 1, 2019. City Council approved the Final Draft and costs September 3, 2019. Staff is submitting the final draft to ARC. ARC stated that it was complete.  
100%
Colquitt Terrace Construction is in progress. Construction - 100%
PD Community Center Parking Lot Project is complete. 100%
SPLOST Resurfacing Bid Package Bartow Paving is in progress.. Design - 100%
SPLOST Proposed Project List and Schedules
List of remaining projects in the SPLOST program turned in for review. 90%
Douglas Boulevard Resurfacing Striping and traffic signal loop installation in progress.  
 
I-20 @ SR 92 Interchange Enhancements

GDOT encroachment permit has been submitted.
Due to planting season requirements, project will bid in late summer.

No bids were received; project is being rebid.

 
Lighting & Banners Phase II Curb and Gutter Construction completed. Project under budget. No change orders. 100% completed
SR92/Dallas Hwy Enhancements Conceptual design is in progress by APD. Concept design - 80%
SR92/Fairburn Road Enhancements Conceptual design is in progress.Also includes Veteran’s Memorial from Campbellton Street to the Old Mill. PIOH was held September 18th. The next step is to generate a GDOT style concept report and complete the concept.    Concept Design – 75% for Fairburn Road, 75% for Veteran’s Memorial.
Cedar Mountain Road Roof has been completed. Interior walls are being installed. HVAC is being installed. Plumbing has started. Generator installed. Working on the sheet rock. 58%
West Court House Square Framing interior walls has started. Roof work starting this week-downstairs concrete flooring started. Contract with Ra-Lin has been signed.
Club Drive Project TBA
Pedestrian Bicycle Plan AECOM is gathering data and mapping. AECOM and the city met with ARC on June 13, 2019.The Steering Committee Meeting is scheduled for September 3, 2019. 10%
I-20 @ Chapel Hill Interchange Douglas County is the project manager. First Steering Committee meeting was held in June. The city is on the steering committee. There are some questions about Freedom Island. Staff presenting to information on Freedom Island on 8-15-19. Went before City Council on August 15, 2019. City Council determined to make it a park. Having it surveyed now. Received a quote from Vansant Campbell for surveying of $1700. 
Comprehensive Transportation Plan Update (CTP) Signed contract with Jacobs. Started study on June 12, 2019. Kick-off meeting with Jacobs on July 9, 2019.Jacobs is doing data collection. Jacobs went to a community event and surveyed citizens on 8-14-19.
Conference Center A/V Equipment/System Met with IT representative. Looking at examples of Audio Visual RFPs in order to get the process started. Currently in the process of getting building plans from architect. AV plans sent to Baker Audio.

LMIG 2019 Resurfacing

 Bids Opened September 20th. CW Matthews was the low bidder.  Contracts are being generated.

Additional Resources

SPLOST ProjectsSPLOST Projects

Downtown Master Plan & 10 Year Strategic PlanDowntown Master Plan & 10 Year Strategic Plan

Douglasville Branding StudyDouglasville Branding Study

Douglasville SPLOST UpdateDouglasville SPLOST Update

State Route 92 ProjectState Route 92 Project

City-County Comprehensive PlanCity/County Comprehensive Plan

Goals and ObjectivesGoals and Objectives (coming soon!)

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Download Acrobat Reader Flash Player Download Flash Player Windows Media Player Download Windows Media Player Microsoft Silverlight Download Microsoft Silverlight Word Viewer Download Word Viewer Excel Viewer Download Excel Viewer PowerPoint Viewer Download PowerPoint Viewer